FPSO Glossary and Methodology

September 2026·6 min read·Reference page

Why this page exists. Most FPSO cost mistakes are vocabulary mistakes — a charter value read as a price, displacement read as topside weight, a financing figure read as contract value. The terms below are used the same way on every page of this site.

How the numbers on this site are built

  1. Public sources only. Every figure comes from company announcements, Petrobras releases, regulator records or specialised trade press, and every page lists its sources with links.
  2. Blank beats estimate. When a value, weight or date could not be confirmed, the cell is left blank. Combined figures (two units, one number) are never split.
  3. Match the contract model first. EPC prices, BOT global prices and charter values describe different economics and are analysed separately.
  4. State the spread. Benchmarks are reported with their observed spread (~9% on $/bpd, ~15% on $/ton) — a margin of error, not a point estimate.
  5. No live-bid information. Nothing from an open tender — pricing, rankings, bidder positioning or internal assessments — is published here.

Glossary

FPSO
Floating Production, Storage and Offloading unit: a ship-shaped facility that processes oil and gas from subsea wells, stores the oil and offloads it to shuttle tankers.
FPU
Floating Production Unit — same function without oil storage (e.g. semi-submersibles P-51, P-52, P-56).
Topside
The processing plant on deck — separation, compression, power generation, water injection — built as modules and lifted onto the hull.
Hull
The floating vessel itself. Can be a newbuild (e.g. SBM Fast4Ward) or a converted VLCC tanker.
Module / moduleiro
A pre-fabricated topside block. A moduleiro is a yard that fabricates or integrates modules.
Integration
Lifting and connecting modules on the hull, then commissioning the plant as one system.
EPC / EPCC
Engineering, Procurement, Construction (and Commissioning): lump-sum build contract; the buyer owns and operates the unit after delivery.
BOT
Build-Operate-Transfer: the contractor builds and operates the unit for a defined period, then transfers ownership to the buyer.
Charter / lease
The contractor owns and operates the FPSO for a long firm term (typically 20–25 years) and is paid a day rate; ownership is not transferred.
Day rate
The daily fee paid under a charter. A charter's headline value is usually day rate × firm term.
Project financing
Debt raised to fund construction of a chartered unit. It is not the contract's value and not the price of the FPSO.
bpd
Barrels of oil per day — the unit's nameplate oil processing capacity.
MMscfd
Million standard cubic feet per day — gas processing capacity.
$/ton
Contract value divided by topside weight. Only comparable when weight basis (topside, not displacement) and contract model match.
$/bpd
Contract value divided by oil capacity. More widely available than weight; still only comparable within one contract model.
Displacement
Weight of water displaced by the whole loaded vessel — hull, ballast and cargo included. Not comparable with topside weight.
Local content (conteúdo local)
Share of a contract's value that must be sourced, fabricated or performed in Brazil, set tender by tender, with penalties for shortfalls.
ANP / CNPE
Brazil's oil regulator (Agência Nacional do Petróleo) and the national energy policy council that sets local content policy.
Pre-salt
Ultra-deepwater carbonate reservoirs below a thick salt layer in the Santos and Campos basins — home of Búzios, Mero, Atapu and Sépia.
eHouse
Pre-fabricated electrical building housing switchgear, transformers and control systems.
Spool
Pre-fabricated piping assembly (pipe, fittings, flanges) delivered ready for installation in a module.
OCTG
Oil Country Tubular Goods — well casing and tubing.
Spread / turret mooring
Ways of anchoring an FPSO: spread mooring fixes its heading; a turret lets it weathervane around a single point.

Put the terms to work: start with the 18-FPSO benchmark or download the dataset (CSV).

Pedro Sotomayor

Pedro Sotomayor, PMP® — Senior Cost Engineer on FPSO projects, 15+ years in offshore cost engineering and project controls (Jurong/Seatrium P-68/P-71, SBM Offshore FPSO Ilhabela). Writes from inside live Brazilian FPSO tenders, using public data only.